Skip to main content
Clear icon
58º

Jaguars ‘Stadium of the Future’ scheduled to open August 2028

Jacksonville and the Jaguars agreement explains how construction and NFL games happen simultaneously

The Jacksonville Jaguars have proposed renovating EverBank Stadium into the “Stadium of the Future.” (Jacksonville Jaguars)

We’re getting a better idea of the timeline for the Jacksonville Jaguars “Stadium of the Future.”

The 1st Downtown Jacksonville organization sent out a timeline on Friday along with the agreement presentation.

Recommended Videos



SEE THE AGREEMENT: Stadium of the Future presentation

The proposed next steps of the process are:

  • June 25: Potential City Council Vote on Legislation
  • October 2024: NFL Owners Approval (75% needed)
  • February 2025: Construction begins
  • 2025 Jaguars Season: Jaguars play in Jacksonville with 60,000+ capacity
  • 2026 Jaguars Season: Jaguars play in Jacksonville with reduced capacity (approx. 43,500)
  • 2027 Jaguars Season: Jaguars play one season away from Jacksonville (Location TBD)
  • August 2028: “Stadium of the Future” opens

The agreement secures the Jaguars stay in Jacksonville for the next 30 years.

Outgoing City Council President Ron Salem says the goal is to vote by June 25. If the council approves the plan this summer, the NFL owners will then vote on it in October.


About the Author
Marilyn Vaca headshot

Marilyn is a Manager of Content and Coverage who supervises News4JAX.com, News4JAX+, along with other News4JAX platforms and channels.

Loading...

Recommended Videos